Power installation process

Electricity registration and registration process

(I) List of information to be provided by the client and its requirements

When a customer applies for new installation or increase of power consumption, he shall provide the power supply company's business window with the approval documents of the power engineering project and relevant power consumption information, including the power consumption location, power use, power nature, power equipment list, and power load. , Security power, power planning, etc., and in accordance with the format specified by the power supply enterprise to fill in the "Customer Electricity Report Form" and complete the necessary procedures.

During the establishment of a new power-receiving project, the user should contact the power supply company to reach an intent agreement on the possibility of power supply, power capacity and power supply conditions of the project before addressing and determining the project.

If the application fails to comply with the provisions of the preceding paragraph, the power supply enterprise shall have the right to refuse to accept its application for electricity use.

If there is a power supply project due to insufficient power supply capacity of the power supply company or government regulations, the power supply company may notify the user to suspend the processing.

Users of low-voltage power supply should provide: load composition and a list of electrical equipment.

1. Information to be provided by residents:

① Identity card of power owner (original and photocopy)

② ID card of the agent (original and photocopy)

③ Owner's ID (original and photocopy)

④ Customer electricity meter installation table (applicable to new installation, capacity increase, capacity reduction)

⑤ Certificate (original and photocopy) of the real estate where the electricity is used (or the "Construction Project Planning Permit", "Construction Land Planning Permit", "Construction Construction Permit" issued by the relevant government department), or the local street office's consent to apply for the certificate )

2.Information for individual industrial and commercial households and corporate legal persons:

① Legal representative ID card (original and photocopy)

② ID card of the agent (original and photocopy)

③Customer's telegram installation meter (applicable to new installation, capacity increase, capacity reduction)

④ Real estate certificate (original and photocopy) of the electricity use location, (or "Construction Project Planning Permit", "Construction Land Planning Permit", "Construction Construction Permit" issued by relevant government departments), or the local street office agrees to apply prove)

⑤ Industrial and commercial business license, institution code certificate, national tax registration certificate (original and photocopy) (do not provide institution code certificate for individual industrial and commercial households)

3. Materials to be provided by state agencies and public organizations:

① Institution code certificate (original and photocopy)

② ID card of the agent (original and photocopy)

③Customer's telegram installation meter (applicable to new installation, capacity increase, capacity reduction)

④ Real estate certificate (original and photocopy) of the electricity use location (or the “Construction Project Planning Permit”, “Construction Land Planning Permit”, “Construction Construction Permit” issued by the relevant government department, or the local street office's consent to apply )

(II) Laws and regulations related to electric power installation and installation:

"Electric Power Law of the People's Republic of China", "Regulations on Power Supply Operation", "Regulations on Electricity Supply and Use", "Technical Guidelines for Urban Distribution Networks in Southern China Power Grid", "Planning and Design of Urban Medium and Low Voltage Distribution Networks in Jiangxi Province and Consumer Power Supply Technology Guidelines".

电力报装流程图

Determine the power supply plan

(I) Determine the basic principles of the power supply plan

The power supply methods provided by power supply companies to users who apply for power consumption shall be based on the safety, economics, reasonableness and ease of management of power supply and use, and in accordance with relevant national policies and regulations, grid planning, power demand, and local power supply conditions. Perform technical and economic comparisons and determine with the user through consultation.

(II) Relevant guidelines for determining the power supply scheme

1.Customers can choose design, construction and equipment materials supply units independently;

2. In accordance with the requirements of the State Electricity Regulatory Commission's "Notice on Strictly Undertaking (Repair, Trial) Power Plant Market Access" (Dianjian Qin [2006] No. 45), the power consumer shall install (repair, test) The power facilities business is handed over to the enterprises that have the qualification certificate and are engaged in the scope of their permits for construction. Qualified electric power construction units can refer to China Electric Power Information Opening Website http://url.alibaba.com/r/aHR0cDovL3d3dy4xMjM5OC5nb3YuY24=List of Licensed Enterprises for "Permit to Install (Repair, Test) Power Facilities".

Sign a contract for power supply and supply

Before the meter is installed, the customer and the local power supply department shall sign the "Power Supply Contract". The customer needs to provide the following documents to sign the "power supply and consumption contract" with the local power supply department:

1. Copy of the ID of the operator;

2.Copy of business license and legal representative's ID card;

3. Entrust the bank to collect the electricity fee contract.